Reported issue ID: 04/2019
Auction restrictions NCG
by AGGM Austrian Gas Grid Management AG
Abstract
Since 2017, restrictive conditions have been announced by the TSO on the PRISMA platform for all annual and quarterly auctions in the German NCG market area. Apparently, the German Federal Network Agency for Electricity, Gas, Telecommunications, Post and Railway (Bundesnetzagentur, BNetzA) requested all TSOs operating in the NCG market area to re-allocate capacities after the annual and quarterly auctions. These restrictions on capacity marketing at interconnection points in the NCG market area are contrary to Article 8 NC CAM.
Category: Cross-border issues with further European relevance
Reported issue
1. Auctioning restrictions in the German NCG market area
Since 2017, restrictive conditions have been announced by the TSO on the PRISMA platform for all annual and quarterly auctions, e.g. the conditions for the quarterly auction on 6 November 2017 by terranets bw:
„RC Lindau, RC Basel: In case the offered capacity for the first quarter 2018 is not sold out during the auction on November 6th, 2017, terranets bw is obliged to re-allocate the respective capacity to other connection points. Therefore it will not be possible to book the unsold capacity in the following monthly, daily and within-day auctions.”
Apparently, the German Federal Network Agency for Electricity, Gas, Telecommunications, Post and Railway (Bundesnetzagentur, BNetzA) requested all TSOs operating in the NCG market area to re-allocate capacities after the annual and quarterly auctions, which is confirmed by corresponding references of the TSOs on the PRISMA platform.
2. Capacity marketing at interconnection points in the NCG market area: non-compliance with the NC CAM
Art 8 (6) NC CAM sets forth that an amount at least equal to 20 % of the existing technical capacity at each interconnection point has to be set aside and offered, with the offering conditions being specified in more detail in Art 8 (7) NC CAM.
Art 8 (7), first sentence, requires the TSO to offer the entire volume set aside (“Any capacity set aside[ …]“).
Art 8 (7)(b) NC CAM lays down that “a further amount at least equal to 10 % of the existing technical capacity at each interconnection point shall first be offered no earlier than the annual quarterly capacity auction as provided for in Article 12, held in accordance with the auction calendar during the gas year preceding the start of the relevant gas year”, i.e. Art 8 (7)(b) NC CAM sets forth both the earliest possible offering time (“shall first be offered no earlier than the annual quarterly capacity auction as provided for in Article 12”) and the TSO’s obligation to offer the unused capacity set aside in the following auctions (“shall first be offered no earlier than the annual quarterly capacity auction as provided for in Article 12”).
It can be derived from Art 8 (3) NC CAM that the TSO has to offer the standard capacity products in their logical order. If a certain capacity product is not marketed completely, i.e. sold out, “the product with the next shortest duration for use during the same period” is offered.
The German Federal Network Agency takes a corresponding legal point of view, holding in its Decision (BK7-15-001 dated 14 August 2015, clause 4.4. (4) (b) (aa)) that the “capacities available from the preceding (annual) auctions” always have to be offered by the TSOs in the quarterly, monthly and daily auctions and/or the within-day auctions.
Articles 11 to 15 NC CAM accordingly define specific rules for the auctions of the individual standard capacity products, including a mandatory formula for each of the standard capacity products. The formulas are all based on the transmission system operator's technical capacity, which is used to calculate the capacity to be offered in each case in the auctions under Articles 11 to 15 by adding and subtracting specific, clearly defined parameters.
An analysis suggests that the re-allocation of capacities is not covered by any of the calculation parameters defined in Articles 11 to 15, and that it is not covered even if the reduction is imposed by the regulatory authority.
Unless the TSOs offer the unused capacities set aside according to Art 8 (6) NC CAM as monthly, daily and within-day standard capacity products, they are - in our point of view - in breach of the requirement to offer capacities set aside according to Art 8 (6) and (7) and do not comply with the calculation formulas of Articles 11 to 15 NC CAM as the re-allocation of capacities is not covered by any of the calculation parameters defined in Articles 11 to 15 NC CAM.
In addition, this approach is in contradiction to the BNetzA’s Decision BK7-15-001 of 14 August 2015.
As a result the TSOs in the NCG market area generate additional income for the capacities actually required by network users because network users are forced to cover their capacity requirements from the quarterly and annual capacity products offered, rather than from ordinary structured capacity bookings.
In general we point out that the auctioning restrictions in the NCG market area make it impossible for market participants to acquire short-term capacity products, and are therefore in stark contrast to the objective to develop a competitive short-term wholesale gas market (e.g. Art 14 (1) (c), Art 16 (2) (b), Annex I 2.1.1. Regulation (EC) No 715/2009, recital 3 Regulation (EU) No 312/2014). On the contrary, they cause sub-optimal market conditions due to inefficient use of the available capacities, which negatively impacts on gas flowing freely across the European Union.
Concerned entities
Network Code on Capacity Allocation Mechanisms, Commission Regulation (EU) 2017/459
- Austria
- France
- Germany
- Italy
- Luxembourg
- Medelsheim (DE) / Obergailbach (FR) (GRTgaz D)
- Medelsheim (DE) / Obergailbach (FR) (OGE)
- Obergailbach (FR) / Medelsheim (DE)
- Oberkappel
- RC Basel
Notified parties
- Bundesnetzagentur (Germany)
- Energie-Control Austria (Austria)
- Bayernets GmbH (DE)
- terranets bw GmbH (DE)
Suggested actions
- ACER
- ENTSOG
- Involved NRA(s)
- Involved TSO(s)
- Adjustement of implementation
comments (0)
IP's concerned
IP |
---|
Medelsheim (DE) / Obergailbach (FR) (GRTgaz D) |
Medelsheim (DE) / Obergailbach (FR) (OGE) |
Obergailbach (FR) / Medelsheim (DE) |
Oberkappel |
RC Basel |
RC Lindau |
Remich |
Steinitz |
VIP Kiefersfelden-Pfronten |
Wallbach |
Informed TSO's
TSO |
---|
Bayernets GmbH (DE) |
terranets bw GmbH (DE) |
Informed NRA's
NRA | Country |
---|---|
Bundesnetzagentur | Germany |
Energie-Control Austria | Austria |
Uploading file
Warning!
You are about to add a file to comment
Please note the file will be visible to all the users and visitors of the Platform
Do not add any confidential documents.
Press "OK" if you still want to add a file, otherwise click "Cancel"
Solution
The solution paper reflects the policy discussions in the underlying bodies of ACER and provides guidance on this matter.
The paper also incorporates the technical inputs from ENTSOG.
Given the auction-based capacity allocation according to CAM NC at IPs and the deviating capacity allocation process at DEPs based on national law, capacity cannot be allocated in a straightforward manner as competing capacities.
Based on that, a reallocation of capacities from IP to DEP might be appropriate as an interim measure for such exceptional cases, if TSOs are guided by a number of predefined criteria:
• This procedure does not endanger security of supply both for customers supplied via the IP or the DEP
• There is comprehensive reasoning that there is indeed potential for competing demand for capacity at both IP and DEP and, in the absence of appropriate network expansion, the level of demand at the DEP cannot be met without allocating capacity from the IP to the DEP
• Capacity may be reallocated to the DEP and will be re-allocated again to the IP if it is no longer needed at the DEP
• The relevant network operator offering the capacity seeks cost-efficient measures to meet the overall capacity demand and render the re-allocation redundant.
• A reallocation of available capacity is the efficient result of an alignment between the involved network operators of the market areas impacted by the reallocation.
• The highest level of transparency is ensured, which involve a yearly alignment meeting between relevant parties, in particular the national regulatory authorities (NRAs’) and network operators of the market areas impacted by the reallocation. Furthermore, shippers are informed of possible reallocation of unbooked capacity prior to the relevant auctions on the capacity booking platforms.
• TSOs and NRAs will make their best efforts to assure that this interim measure lasts the shortest period of time possible.
For details, reference is made to the two Solution related documents below.